Evaluation of Factors Affecting the Delay in a Construction Project of Dr. Iskak’s Hospital Pavilion of Tulungagung District
Journal: International Journal of Scientific Engineering and Science (Vol.2, No. 9)Publication Date: 2018-10-15
Authors : Evi Purvitasari Subandiyah Azis Tiong Iskandar;
Page : 38-44
Keywords : Building; design changes; completion of project; delay.;
Abstract
—In its implementation, the Dr. Iskak's Hospital Pavilion of Tulungagung District, which was built in the fiscal year of 2016, experienced obstacles that had caused delays in the completion of its construction project. The delay reached 15% of the specified time. This research was conducted to find out and obtain the factors affecting the delay and to obtain the most dominant factors in influencing it, so that the right action to minimize the occurrence of delays in the completion of the work can be determined. The data analysis methods were factor analysis and multiple linear regression analysis using the SPSS program to answer the questionnaire distributed to 37 respondents consisting of the owner, contractor and supervisory consultant. The findings showed that all factors simultaneously had an effect on the delay in completing the project with a value of Fcalculate = 6.304>Ftable = 2.346. Meanwhile, partially the factors that have a positive and significant effect on the delay in project completion are Design Changes, Work Environment, and Workers. The calculation of multiple linear regression analysis found that the most dominant factor affecting the delay in the completion of the project is the Design Change factor with a standardized coefficient of β of 0.417. The actions required to be taken to overcome this are to immediately make changes to the contract (amendment to the contract) due to changes in the scope of the work.
Other Latest Articles
- Priority Scale Analysis Using Analytical Hierarchy Process (AHP) to Determine Traditional Market Development in Tulungagung District
- A Method to Design Vibratory Bowl Feeder by Using Numerical Simulation Analysis
- Optimization of the Combination of Heavy Equipment Use in Land-Filling Work in Terms of Time and Cost in the Construction Project of Job Training Center at Ende District of East Nusa Tenggara
- Classification of Phosphodiesterases and the Therapeutic Effects of their Inhibitors (Review)
- A Simple Synthesis of Pd@Au Core/Shell Nanosheets
Last modified: 2018-10-18 14:41:17