Reduction in Setup Change Time of a Machine in a Bearing Manufacturing Plant Using SMED and ECRS
Journal: International Journal of Engineering Research (IJER) (Vol.3, No. 5)Publication Date: 2014-05-01
Authors : Gaurav J. Pawar; Nishant S. Sirdeshpande; Aniket B. Atram; Prachi R. Patil;
Page : 321-323
Keywords : SMED; ECRS; Setup time; Line layout;
Abstract
Single minute exchange of dies along with ECRS can be used efficiently to reduce setup time. The present paper provides an analysis of current changeover methods of bearing ring grinding machine in a manufacturing plant having line layout. The study gives methods for reducing setup time using above mentioned tools.
Other Latest Articles
- Embedded ANFIS as a Supervisory Controller for a 6-DOF Robotic Arm
- Design of Solar Steam Irrigation Pump
- Optimization of Lung Cancer using Modern Data Mining Techniques
- Performance Analysis and Optimization of Hmipv6 and Fmipv6 Handoff Management Protocols
- Fuzzy Logic Controlling of a Single Phase Seven-Level Grid-Connected Inverter for Photovoltaic system
Last modified: 2014-07-16 01:43:53