Tracking Predictive Gantt Chart for Proactive Rescheduling in Stochastic Resource Constrained Project Scheduling
Journal: Journal of Information and Organizational Sciences (JIOS) (Vol.42, No. 2)Publication Date: 2018-12-10
Authors : Mario Brčić; Danijel Mlinarić;
Page : 179-192
Keywords : Project scheduling; Proactive-reactive scheduling; Gantt chart; Stochastic RCPSP;
Abstract
Proactive-reactive scheduling is important in the situations where the project collaborators need to coordinate their efforts. The coordination is mostly achieved through the combination of the shared baseline schedule and the deviation penalties. In this paper, we present an extension of predictive Gantt chart to the proactive-reactive scheduling needs. It can be used to track the evolution of the relationship between dynamic and static elements through the time. The dynamic elements are evolving probability distributions due to the uncertainty and revealed information. The static elements are time-agreements in the baseline schedule. We demonstrate that in the stateof-the-art proactive-reactive scheduling, the baseline schedule is agnostic to the information received during the project execution. The sources of such inflexibility in the problem model and the scheduling methods are analyzed. The visualization is highlighted as a precursor to developing new methods that proactively change the baseline schedule in accordance with the gained information.
Other Latest Articles
- Beyond Knowledge Integration Barriers in ERP Implementations: An Institutional Approach
- Modern lightning protection of buildings and constructions. Part 2
- How much is the fire “cost” in the modern world?
- Relevance of studies of the level of awareness of students on fire safety living in dormitories
- Study of the operational characteristics of fireproof coatings based on epoxy resins modified with astralenes
Last modified: 2020-03-13 17:47:27