Shovel-Truck Haulage Analysis Using Stochastic Discrete Event Simulation
Journal: International Journal of Science and Research (IJSR) (Vol.5, No. 11)Publication Date: 2016-11-05
Authors : Raymond Ninnang Tiile; Felix Adaania Kaba; Nassib Aouad; Francis Arthur;
Page : 495-498
Keywords : Mine planning; Arena stochastic discrete simulation; Productivity; Optimization; Profitability;
Abstract
Detailed weekly mining plans are prepared by Perseus Mining Ghana Limited (PMGL) geared towards the accomplishment of monthly mining targets. Weekly and daily mining volumes are established primarily based on the excavator dig rates and excavator (shovel) availabilities and utilizations. A daily mining target of 15, 000 BCM of material is expected to be mined by two (2) shovels and as many as twenty (20) dump trucks over a period of one (1) month. Given the size of pit and the number of dump trucks, truck queuing and congestion in-pit and on roads with their downstream consequences is highly anticipated. This paper therefore seeks to address the above challenge by using an Arena-based stochastic discrete event simulation to derive an optimum shovel-truck combination that improves productivity, minimizes operation cost and maximizes overall profitability.
Other Latest Articles
- Aeromagnetic Anomalies, Limited Ground Magnetic and Gravity Survey of NE Kogi State / NW Benue, Nigeria
- Plight of Teachers in Areas with Unstable Peace and Order: Some Stories to Tell
- Copper Slag Partially Replaces Fine Aggregate in M 25 Concrete: A Comparative Study of Compressive Strength Responses
- Antioxidant Activity of the Major Soldier Salivary Glands Extracts of the Termite Macrotermes bellicosus
- Adaptive Contrast Enhancement and White Balancing Integration for Image Enhancement Based on Non-linear Generalized Equalization Model
Last modified: 2021-07-01 14:47:12