CRASHING CONSTRUCTION PROJECT SCHEDULES BY RELOCATING RESOURCES
Journal: International Journal of Advanced Research in Engineering and Technology (IJARET) (Vol.10, No. 6)Publication Date: 2019-12-23
Authors : Aravind G Dhivya S B. Manoharan M. Jeganathan;
Page : 544-560
Keywords : Construction project management; construction project scheduling; resource allocation; resource-constrained project scheduling problem; schedule optimization;
Abstract
A variety of schedule compression techniques are used to get delayed construction projects ‘‘back on tracks''. This paper presents a new optimization approach to schedule crashing by relocating some of the workers from non-critical to critical processes (changing composition of crews using the initial pool of workers) and employing additional resources. The authors describe their idea in the form of a mixedinteger linear problem. A numerical example illustrates the merits of the proposed approach. The method may become a practical support in construction scheduling decisions.
Other Latest Articles
- CHARACTERIZATION OF BIODIESEL FOR USE AS A FUEL IN COMPRESSION IGNITION ENGINE
- DESIGN OF SECURITY ALGORITHM FOR CONTROL SYSTEMS WITH FINITE STATE AUTOMATA
- Weslaw Borys
- Архітектурні назви, мотивовані дієсловом *stati+/staviti, в українській мові та мовах балкано-слов’янського континууму
- Proper names as a natural category: proverbial phrases with cultural names from the perspective of eponymy research
Last modified: 2022-03-10 13:16:57